icon-arrow-right icon-play icon-close
HomeNewsWorks progressing on C2V+ Congleton site

Works progressing on C2V+ Congleton site

Recent

C2V+, a VolkerStevin and Jacobs joint venture, are making good progress with the ongoing construction work at our Congleton Wastewater Treatment Works (WwTW) site. The team’s main focus to date has been on the Formwork, Reinforcement and Concrete (FRC) works, and the main structures are now built and have been water tested, enabling the team to begin backfilling. The below ground civils work, access steel work and general mechanical installations are now underway, as well as the drainage pipework installation.

IMG-20240207-WA0002.jpg

The tertiary solids removal skid and vessels have been placed into position and the tertiary solid removal clean backwash tank has also been installed and tested. The team has installed pumps and pipework to the mixed liquors suspended solids slab, along with the steelwork walkways to the new activated sludge process. The activated sludge process blower pipework installation has commenced and scraper bridges have been installed to two new final settlement tanks (FST’s).

The team are also making progress with the electrical work, with the low voltage and switchboard kiosks and motor control centres built and ready to be delivered later this month. The tertiary solid removal motor control centre is ready to be delivered and the activated sludge process and tertiary kiosks are currently being manufactured. The main design for on-site electrical install works is underway and the FST scraper bridge control panel has been manufactured and factory tested.

Over the coming months the team will begin work on extending the existing inlet channel, they will also be building new structures that are within the inlet area, this will include a dirty backwash tank and primary settlement tank distribution chamber. The team will continue the below ground process pipework and will start the construction of the main cable duct and pit runs.

Testing and commissioning of the new equipment is due to start in May, with process commissioning commencing in June.

 

News

More news

VolkerStevin is awarded second phase of the Rochdale and Littleborough Flood Risk...

VolkerStevin has been awarded the second phase, Phase 1B, of the Rochdale and Littleborough Flood Risk Management Scheme,...

International Women's Day

At VolkerStevin, we are passionate about the benefits a diverse workforce and inclusive culture can bring to our business....

VolkerGround Engineering at Macclesfield

VolkerGround Engineering recently delivered a project at Macclesfield Wastewater Treatment Works on behalf of C2V+, a joint...

+