We use necessary cookies to make our site work. We’d also like to set optional social media cookies to improve your experience of using our site and Google Analytics cookies to help us understand how you use it. We won’t set optional social media cookies or Google Analytics cookies unless you enable themby confirming your choices below. Using this tool will set a cookie on your device to remember your preferences. For more detailed information about the cookies we use, see our Cookies Policy.
Necessary cookies
Necessary cookies enable core functionality such as security, network management, and accessibility. You may disable these by changing your browser settings, but this may affect how the website functions.
If you would like to access social media features, including viewing streamed video content, please provide your consent to the placing of cookies by social media networks, by ticking the box to the left. These networks may have access to follow you and use your online behaviour for other purposes.
We use Google Analytics cookies to help us to improve our website by collecting and reporting information on how you use it. For more information on how these cookies work please see our Cookies policy
The Portsmouth Upper Harbour Ammunition Facility (UHAF) project is the latest VolkerStevin project to achieve a CEEQUAL award, and demonstrates its strong commitment to environmental and social performance. The project, a new ammunition facility at Portsmouth Naval Base that forms a key component to the government's future defence strategy, achieved a score of ‘Very Good' from CEEQUAL.
Some of the extra measures taken by Portsmouth UHAF to ensure sustainability on the project include:
99% of waste recycled at a local recycling facility
Re-use of an existing hard-standing area used for the site compound, avoiding the use of greenfield land take and the need to import aggregates to create a suitable area
All timber certified as being responsibly sourced through Chain of Custody evidence, in accordance with the government's timber procurement policy
As many of the concrete elements as possible were pre-cast in order to reduce the need to pour concrete in the harbor, reducing risk of water contamination
All steel piles and pre-cast concrete units were imported to the site by sea rather than by road, reducing the impact of the project on the local roads as well as the associated carbon emissions from transport
Works were undertaken from the deck of a barge, enabling materials and liquids to be stored appropriately
Two wind turbines were installed to charge a battery pack in order to minimise the need for generators during periods of low energy demand
During the construction phase, a timer was installed on the site compound floodlights to ensure it was switched off overnight, minimising both nuisance to local residents and electricity consumption
Energy use was tracked monthly using a spreadsheet and displayed on site notice boards to ensure everyone was aware of energy consumption
Stuart Eckersley, VolkerStevin contracts director, said: "VolkerStevin is dedicated to ensuring that all aspects of site safety and environmental control, including reduction in waste, exceed the expectations of clients and the local community.
"We are delighted to have achieved this award, which demonstrates the proactive approach taken to achieve environmental and social performance on the project."